Queens Water Tunnel #2, Stage #2 |
|
Project Location : |
Queens, New York City, NY, USA
|
|
Owner : |
DEP (Department of Environmental Protection), New York City
|
|
Design Firm : |
-
|
|
Contractor : |
GPS (Grow-Perini-Skanska)
|
|
Construction Manager : |
-
|
|
|
|
|
Purpose of the Tunnel : |
To improve fresh water distribution throughout the city
|
| Total Tunnel Length : | 4.72-mile
|
| Excavated Diameter : | 23.18-ft
|
| Secondary Lining : | -
|
|
Excavation Start : |
1996
|
|
Excavation End : |
1999
|
|
Bid Value : |
170,000,000 USD
|
|
Geology : |
Gneiss
formation including biotite-hornblende gneiss intermixed with granitic
gneiss, amphibolite, pegmatite, and biotite schist.
|
|
TBM Specifications : |
Robbins
235-282 high-performance tunnel-boring machine. 23.18-ft cutterhead diameter 50 19-inch disc cutters with 0.75-inch tip with and 70,000 lbs max. cutter load 4220 hp cutterhead power 3,500,00 lbs total installed thrust
|
|
Publications : |
Khalighi B. B., Diehl J. J., "High Performance Tunnel Boring Machine for Queens Water Tunnel, No. 3: A Design and Case History", RETC 1997.
Merguerian C., Ozdemir L., "Rock Mass Properties and Hard Rock TBM Penetration Rate Investigations, Queens Tunnel Complex, NYC Water Tunnel #3, Stage #2", RETC 2003.
|