Chattahoochee Tunnel

 

Project Location :

Atlanta, Georgia, USA

 

Owner :

Cobb County Water System (CCWS)

 

Design Firm :

Jacobs Associates, Inc.

 

Contractor :

Gilbert/Healy

 

Construction Manager :

Parsons Engineering Science in conjunction with Jacobs Associates, Inc.

 

 

Purpose of the Tunnel :

To provide sewerage conveyance for flows from eastern Cobb County, an area that is currently being served by existing sewers that are near capacity.

 

 

 

Total Tunnel Length :

9.5-mile

 

Excavated Diameter :

18-ft

 

Secondary Lining :

1-ft thick in-place concrete lining

 

Excavation Start :

June 2000

 

Excavation End :

Planned for May 2004

 

Bid Value :

133,600,000 USD

 

Geology : The rocks in the area of the Chattahoochee Tunnel Project are mainly medium grade metamorphic rocks with a small percentage of granitic rocks. Along the tunnel alignment the metamorphic rocks include phyllonite, mica schist, arkosic and granitic gneiss, quartzite and amphibolite. The granitic rocks include some massive "granites" of quartz-diorite composition and smaller lenses of granite and pegmatite. The phyllonite, mica schist, and arkosic gneiss rocks are moderately to highly foliated and anisotropic. On average, the foliation in the area of the tunnel strikes N52°E east and dips 35° to the southeast.

 

 

 

TBM Specifications :

Robbins Model 235-282

18-ft cutterhead diameter

39 19-inch Disc Cutter (70,000 lbs max. cutter load)

2,954 hp cutterhead power

3,000,00 lbs total installed thrust

 

 

Publications :

Kimball R. W., Estep F. B., Easterling D., "Chattahoochee Tunnel", RETC 2003.


 

Back to "Hard Rock Tunneling" Page